Africa’s largest copper complex has begun receiving round-the-clock electricity from a 233 MWp solar farm paired with a 526 MWh battery-storage system, marking a significant step in the integration of renewable energy into large-scale mineral production in the Democratic Republic of Congo (DRC). The facility at the Kamoa-Kakula Copper Complex reached commercial operation in August and is designed to provide at least 30 MW of continuous power, including after sunset.
Developed by independent power producer CrossBoundary Energy, the solar-plus-storage project addresses one of the most consequential constraints facing African mining: reliable and affordable electricity. For Kamoa-Kakula, the development also demonstrates how mining companies and private power developers are increasingly building dedicated energy infrastructure around strategic mineral assets rather than relying entirely on constrained national grids.
Power Security Becomes a Mining Imperative
Kamoa-Kakula already draws substantial electricity from hydropower, but instability in the DRC’s power system has previously required the complex to rely on diesel generation and imported electricity. For an operation producing hundreds of thousands of tonnes of copper annually, such interruptions are more than an energy-management issue. They represent a direct production and cost risk.
The new facility changes part of that equation. Solar panels generate electricity during daylight hours, while the battery stores excess generation and releases it when solar output declines. This allows the system to provide a more predictable electricity supply rather than simply supplying power when the sun is available.
CrossBoundary says the system’s guaranteed contribution is at least 30 MW of baseload power, while the project can reduce exposure to diesel-price volatility and fuel-supply disruptions. The facility does not power the entire copper complex. Hydropower, imported electricity and other sources remain part of the overall energy mix.
That distinction is important: the significance of the project lies not in replacing the grid entirely, but in demonstrating how renewable generation and storage can be integrated into a large industrial power system.
A New Model for Mining Power
The project reflects a broader change in the relationship between mining and electricity infrastructure.
Historically, large mines in Africa have often depended on national utilities to provide the power required for extraction and processing. But where grids face shortages, transmission constraints or reliability problems, the economics of mining can become closely tied to the performance of the power system.
Kamoa-Kakula illustrates an alternative model:
Mining project
↓
Private power developer
↓
Dedicated solar generation
↓
Battery storage
↓
Firm renewable power
↓
More resilient mining operations
This model could become increasingly relevant across Africa’s mining belts.
For investors, the opportunity is not limited to mining companies. It extends to independent power producers, battery developers, infrastructure funds, equipment suppliers and financiers capable of building dedicated energy systems for industrial consumers.
Copper and Energy Security Are Becoming Interlinked
The timing of the investment is particularly significant because copper is becoming increasingly important to the global energy system. Copper is required extensively in electricity grids, renewable-energy systems, electric vehicles, data centres and other electrification infrastructure.
That creates an important paradox for copper producers. The world needs substantially more copper to build the energy transition, but producing that copper requires enormous quantities of energy.
Kamoa-Kakula’s solar-and-storage investment addresses part of that challenge by connecting the production of a critical mineral with lower-carbon electricity infrastructure.
The result is a potentially reinforcing relationship:
Renewable energy → powers; Copper production → supplies; Electrification infrastructure → which drives Further renewable-energy demand
This is increasingly becoming an important investment theme across global mining.
Kamoa-Kakula Is Scaling Its Energy Platform
The solar facility is not an isolated investment. Kamoa-Kakula is developing a broader renewable-energy programme designed to increase its supply of firm solar power.
Earlier plans indicated that two privately funded solar-and-storage projects could eventually provide a combined 60 MW of baseload capacity, incorporating approximately 433 MWp of solar generation and 1,107 MWh of battery storage.
The complex is targeting approximately 120 MW of on-site solar baseload supply by the end of 2027 as it works towards producing around 500,000 tonnes of copper annually from 2028.
The relationship between these two targets is strategically important. Increasing copper output requires increasing energy availability.
Rather than treating electricity as an external constraint, the project is increasingly treating energy infrastructure as part of the mining expansion strategy itself.
The Mining Complex Is Already an Industrial Platform
Kamoa-Kakula produced approximately 388,800 tonnes of copper in 2025 and generated about $3.28 billion in revenue, according to the reporting. The complex also includes a 500,000-tonne-per-year copper smelter, commissioned in 2025 and described as Africa’s largest copper smelter.
This adds another dimension to the energy requirement. The project is no longer simply about extracting copper ore.
It increasingly combines:
- Mining
- Concentration
- Smelting
- Energy infrastructure
- Potential downstream value creation
That makes reliable electricity even more critical.
The more processing that takes place within Africa, the more important energy availability becomes to the competitiveness of the entire value chain.
A Private-Capital Solution to a Public Infrastructure Gap
One of the most interesting aspects of the project from an investment perspective is the role of private capital.
The solar-and-storage facility was developed by CrossBoundary Energy rather than being delivered solely through public infrastructure spending.
The power purchase agreement between CrossBoundary Energy and Kamoa Copper was signed in 2025, with the project moving to commercial operation in roughly 16 months. CrossBoundary has described the delivery period as substantially faster than the average reported for comparable African solar-and-storage projects, although that comparison has not been independently verified.
The model demonstrates how bankable industrial demand can support private investment in energy infrastructure. Rather than waiting for grid expansion to catch up with mining requirements, the mine provides an anchor customer around which a private energy project can be structured.
That approach could be replicated in other energy-intensive sectors, including:
- mining;
- metals processing;
- cement;
- industrial parks;
- data centres;
- manufacturing;
- and large agricultural processing facilities.
The DRC’s Wider Infrastructure Challenge
The development also highlights one of the DRC’s central economic contradictions. The country possesses some of the world’s most important deposits of copper and cobalt, yet inadequate electricity and transport infrastructure continue to constrain the ability to fully exploit those resources.
This means the country’s mineral opportunity is inseparable from its infrastructure challenge.
The Kamoa-Kakula model offers one response: build infrastructure directly around commercially viable resource projects. But the broader development question remains whether such privately financed infrastructure can eventually connect with wider national and regional systems, creating benefits beyond individual mines.
For the DRC, that distinction will be important. Mine-specific infrastructure can unlock production quickly. Shared infrastructure can transform an entire mining region.
Strategic Context: Critical Minerals Need Critical Infrastructure
The Kamoa-Kakula development comes as the global race for critical minerals intensifies. Copper is increasingly regarded as strategically important to electrification, grid expansion, renewable energy, electric mobility and digital infrastructure.
Africa possesses substantial copper resources, particularly across the Central African Copperbelt, but the ability to convert those resources into competitive supply depends on infrastructure.
That includes:
- Power
- Rail
- Roads
- Ports
- Processing
- Water
- Digital infrastructure
The solar-plus-storage project demonstrates one increasingly important component of that equation.
If Africa wants to become a larger supplier of processed critical minerals, it must also become capable of supplying the reliable energy required to process them.
AFNIS Insight
The significance of Kamoa-Kakula’s solar-and-storage project extends well beyond renewable energy; It represents an emerging model in which energy security is designed into the architecture of critical-mineral development.
For mining companies, the lesson is increasingly clear: electricity is not merely an operating input. In regions where grid reliability is uncertain, it can determine the pace, cost and bankability of an entire mineral project.
This creates a new infrastructure opportunity around Africa’s resource economy. Independent power producers, battery-storage companies, infrastructure funds and developers can increasingly partner directly with mines to build dedicated energy systems backed by long-term industrial demand.
For Africa’s critical-minerals strategy, the message is even broader.
The continent cannot build the energy transition with minerals produced through infrastructure systems that remain unreliable.
Kamoa-Kakula’s approach points towards a different model: pairing mineral development with dedicated clean power, storage and industrial infrastructure from the outset.
As copper demand rises, that model could become increasingly important; not only for reducing mining emissions, but for making Africa’s mineral supply chains more reliable, more competitive and more investable.